Site Visit March 2023
Got to take my Architect on site to review things as we are preparing the Outline approval application for Town and Country Planning.
Roads are being paved! Water, Natural Gas, electricity and Telecoms have been run throughout the park. Was told that everything should be completed in mid April 2023.
Some issues arose:
- a transformer pad has been built on or very close to the site
- the site has a high clay content which will make the foundation more expensive.