Site Visit March 2023
Got to take my Architect on site to review things as we are preparing the Outline approval application for Town and Country Planning. Roads are being paved! Water, Natural Gas, electricity and Telecoms have been run throughout the park. Was told that everything should be completed in mid April 2023. Some issues arose: a transformer…
-
Delayed again
Sure enough, I just heard from eTeck that the park is now delayed until March 2023. Good thing I’m not holding my breath! We have however been getting our outline approval application put together and have purchased the pre-fab structure that is going to house the brewery. We are heading into a very busy time!
-
Site Visit 2022-09-27
-
Delayed again
-
Slowly, slowly. Slowly getting faster (hopefully!)
-
Progress – somewhat
-
The Beginning